UPDATE OF IT MODERNISATION PROJECT
The latest position of implementation is as follows:
- Primary Data Centre has started functioning at Navi Mumbai since 3rd April, 2013. Disaster Recovery Centre has been powered on at Mysore on 15-05-15.
- 27702 Departmental Post offices including mail offices and administrative offices have been networked at single Wide Area Network (WAN) and connected to Data Centre.
- Core Banking Solution (CBS) has been rolled out in 9583 Post Offices.
- ATMs have been installed in 125 locations.
- Core Insurance solution (CIS-PLI) has been rolled out in 20378 Post Offices.
- CSI pilot roll out has started in Mysore Division of Karnataka Circle on 01.10.2015.
- Rural Hardware vendor has been finalized and contract has been signed. Development of software is underway and once it is ready deployment of hardware in pilot Branch Post Offices will start.