The latest position of implementation is as follows:
- Primary Data Centre has been deployed and started functioning at Navi Mumbai since 3rd April, 2013. Disaster Recovery Centre has been powered on at Mysore on 15-05-15.
- 27680 Departmental Post offices including mail offices and administrative offices have been networked at single Wide Area Network (WAN) and connected to Data Centre.
- Core Banking Solution (CBS) has been rolled out in 5571 Post Offices.
- ATMs have been installed in 124 locations.
- Core Insurance solution (CIS-PLI) has been rolled out in 15125 Post Offices.
- Rural Hardware vendor has been finalized and contract has been signed. Supply of Rural Hardware devices in Pilot BOs will start in January 2016.